Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
2013 STREET RESURFACING PROGRAM |
Description: Resurface various streets in Burlingame
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | Burlingame |
Zip Code | 94010 |
Senate District |
04 |
Assembly District | |
Congressional District | 19 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
Public Works | Kevin Okada | 650 558-7213 | kokada@burlingame.org | |
Right of Way Phase |
|||||
Construction Phase |
Public Works | Kevin Okada | 650 558-7213 | kokada@burlingame.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$411 | $0 | $411 | ||||
Non-bond Funding | |||||||
Local** |
$589 | $0 | $589 | ||||
Total**** | $1,000 | $0 | $1,000 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$50 | $0 | $50 | $45 | $45 | $5 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$950 | $0 | $950 | $844 | $844 | $106 | |
Total* | $1,000 | $0 | $1,000 | $889 | $889 | $111 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2013 02/01/2013 |
|
01/01/2013 02/01/2013 |
100 | 01/01/2013 02/06/2013 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2013 03/01/2013 |
|
02/01/2013 03/01/2013 |
100 | 11/05/2012 02/28/2013 |
3 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2013 10/01/2013 |
|
07/01/2013 10/01/2013 |
100 | 07/25/2013 01/31/2014 |
-1 -4 |
Begin Closeout Phase
End Closeout Phase |
10/01/2013 11/01/2013 |
|
10/01/2013 11/01/2013 |
100 | 02/01/2014 06/09/2014 |
-4 -7 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$411,000 |
Current Approved: |
$411,000 |
Actual Expenditures: |
$411,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle