2013 STREET RESURFACING PROGRAM

Description: Resurface various streets in Burlingame

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City Burlingame
Zip Code 94010
 
Senate District
04
Assembly District
Congressional District 19
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Public Works Kevin Okada 650 558-7213   kokada@burlingame.org
Right of Way Phase
 
Construction Phase
Public Works Kevin Okada 650 558-7213   kokada@burlingame.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$411 $0 $411
Non-bond Funding
Local**
$589 $0 $589
 
Total**** $1,000 $0 $1,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$50 $0 $50 $45 $45 $5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$950 $0 $950 $844 $844 $106
 
Total* $1,000 $0 $1,000 $889 $889 $111

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2013 

02/01/2013 
 

 
01/01/2013 

02/01/2013 
100  01/01/2013 

02/06/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2013 

03/01/2013 
 

 
02/01/2013 

03/01/2013 
100  11/05/2012 

02/28/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

10/01/2013 
 

 
07/01/2013 

10/01/2013 
100  07/25/2013 

01/31/2014 
-1 

-4 
Begin Closeout Phase

End Closeout Phase
10/01/2013 

11/01/2013 
 

 
10/01/2013 

11/01/2013 
100  02/01/2014 

06/09/2014 
-4 

-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$411,000
Current Approved:
$411,000
Actual Expenditures:
$411,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle