SIDEWALK IMPROVEMENT - VARIOUS LOCATIONS |
Description: Repair various concrete sidewalk locations
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | Brisbane |
Zip Code | 94005 |
Senate District |
08 |
Assembly District | 19 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Separated Bike/Pedestrian Paths |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Brisbane | Karen Kinser | 415-508-2133 | kkinser@ci.brisbane.ca.us | |
Design (PS&E) Phase |
City of Brisbane | Karen Kinser | 415-508-2133 | kkinser@ci.brisbane.ca.us | |
Right of Way Phase |
City of Brisbane | Karen Kinser | 415-508-2133 | kkinser@ci.brisbane.ca.us | |
Construction Phase |
City of Brisbane | Karen Kinser | 415-508-2133 | kkinser@ci.brisbane.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$50 | $0 | $50 | ||||
Non-bond Funding | |||||||
Local** |
$50 | $0 | $50 | ||||
Total**** | $100 | $0 | $100 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$100 | $0 | $100 | $124 | $124 | $-24 | |
Total* | $100 | $0 | $100 | $124 | $124 | $-24 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/10/2012 01/14/2013 |
|
12/10/2012 01/14/2013 |
100 | 12/10/2012 01/21/2013 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/14/2013 03/01/2013 |
|
01/14/2013 03/01/2013 |
100 | 01/14/2013 03/01/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/14/2013 01/14/2013 |
|
01/14/2013 01/14/2013 |
100 | 01/14/2013 01/21/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2013 07/01/2013 |
|
05/01/2013 07/01/2013 |
100 | 08/26/2013 02/24/2014 |
-4 -8 |
Begin Closeout Phase
End Closeout Phase |
08/15/2013 10/15/2013 |
|
08/15/2013 10/15/2013 |
75 | 02/25/2014 01/15/2015 |
-6 -15 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Separated Bike/Pedestrian Paths |
Bond Funding Cost | |
---|---|
Adopted: |
$50,000 |
Current Approved: |
$50,000 |
Actual Expenditures: |
$50,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle