LA COLINA DRIVE PAVEMENT REHAB

Description: Pavement Rehab on La Colina Drive

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City
Zip Code
 
Senate District
33
Assembly District 71
Congressional District 45
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
Right of Way Phase
 
Construction Phase
County of Orange Joel Samonte 714-245-4558   joel.samonte@ocpw.ocgov.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$764 $51 $815
Non-bond Funding
Local**
$917 $86 $1,003
 
Total**** $1,681 $137 $1,818

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$153 $0 $153 $93 $93 $60
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,528 $137 $1,665 $1,520 $1,520 $145
 
Total* $1,681 $137 $1,818 $1,613 $1,613 $205

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/09/2011 

12/30/2012 
 

 
05/09/2011 

12/30/2012 
100  04/26/2011 

12/04/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2012 

12/30/2012 
 

 
06/01/2012 

12/30/2012 
100  05/13/2011 

12/19/2012 
13 

Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/30/2013 

08/27/2013 
 

 
06/30/2013 

08/27/2013 
100  04/23/2013 

08/26/2013 


Begin Closeout Phase

End Closeout Phase
08/30/2013 

10/15/2013 
 

 
08/30/2013 

10/15/2013 
100  08/27/2013 

04/03/2014 


-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$764,000
Current Approved:
$815,000
Actual Expenditures:
$760,008

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle