ROAD REHAB PROGRAM

Description: Reconstruct and Resurface AC Pavement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City Half Moon Bay
Zip Code 94019
 
Senate District
08
Assembly District 19
Congressional District 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Half Moon Bay Mo Sharma, City Engineer (650)726-8265   msharma@hmbcity.com
Design (PS&E) Phase
City of Half Moon Bay Mo Sharma, City Engineer (650)726-8265   msharma@hmbcity.com
Right of Way Phase
City of Half Moon Bay Mo Sharma, City Engineer (650)726-8265   msharma@hmbcity.com
Construction Phase
City of Half Moon Bay Mo Sharma, City Engineer (650)726-8265   msharma@hmbcity.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$242 $0 $242
Non-bond Funding
Local**
$242 $0 $242
 
Total**** $484 $0 $484

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$484 $0 $484 $685 $685 $-201
 
Total* $484 $0 $484 $685 $685 $-201

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

11/01/2012 
 

 
 

11/01/2012 
100  11/01/2012 

11/01/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/12/2012 

01/30/2013 
 

 
11/12/2012 

01/30/2013 
100  12/01/2012 

02/28/2013 
-1 

-1 
Begin Right of Way Phase

End Right of Way Phase
01/02/2013 

01/31/2013 
 

 
01/02/2013 

01/31/2013 
100  01/02/2013 

02/28/2013 


-1 
Begin Construction Phase

End Construction Phase
03/01/2013 

12/01/2013 
 

 
03/01/2013 

12/01/2013 
100  08/20/2013 

01/21/2014 
-6 

-2 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/30/2013 
 

 
11/01/2013 

12/30/2013 
100  01/22/2014 

04/16/2014 
-3 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$242,000
Current Approved:
$242,000
Actual Expenditures:
$242,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle