RESURFACE VARIOUS STREETS

Description: Resurface Various Streets

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City
Zip Code
 
Senate District
08
Assembly District 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
County of San Mateo Department of Public Works Gil Tourel 650-599-1482   gtourel@smcgov.org
Design (PS&E) Phase
County of San Mateo Department of Public Works Gil Tourel 650-599-1482   gtourel@smcgov.org
Right of Way Phase
County of San Mateo Department of Public Works Gil Tourel 650-599-1482   gtourel@smcgov.org
Construction Phase
County of San Mateo Department of Public Works Zack Azzari 650-599-1450   zazzari@smcgov.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$605 $0 $605
Non-bond Funding
Local**
$1,245 $0 $1,245
 
Total**** $1,850 $0 $1,850

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,850 $0 $1,850 $1,355 $1,355 $495
 
Total* $1,850 $0 $1,850 $1,355 $1,355 $495

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2012 

10/15/2012 
 

 
10/01/2012 

10/15/2012 
100  12/26/2012 

01/28/2013 
-2 

-3 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2012 

03/30/2013 
 

 
11/01/2012 

03/30/2013 
100  10/15/2012 

03/11/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/15/2013 

11/01/2013 
 

 
07/15/2013 

11/01/2013 
100  07/09/2013 

05/19/2014 


-7 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/30/2013 
 

 
11/01/2013 

12/30/2013 
100  05/20/2014 

08/11/2014 
-7 

-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$605,000
Current Approved:
$605,000
Actual Expenditures:
$605,000

 

Status as of December 31, 2023.