HWY 111/WASHINGTON STREET IMPROVEMENTS

Description: Improve Hwy 111 at Washington Street

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City La Quinta
Zip Code
 
Senate District
37
Assembly District 80
Congressional District 45
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Peak Period Time Savings (minutes)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of La Quinta Bryan McKinney (760) 777-7045   bmckinney@la-quinta.org
Design (PS&E) Phase
City of La Quinta Bryan McKinney (760) 777-7045   bmckinney@la-quinta.org
Right of Way Phase
City of La Quinta Bryan McKinney (760) 777-7045   bmckinney@la-quinta.org
Construction Phase
City of La Quinta Bryan McKinney (760) 777-7045   bmckinney@la-quinta.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$283 $0 $283
Non-bond Funding
Local**
$283 $0 $283
 
Total**** $566 $0 $566

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$566 $0 $566 $743 $743 $-177
 
Total* $566 $0 $566 $743 $743 $-177

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/22/2012 

10/10/2012 
 

 
06/22/2012 

10/10/2012 
100  06/22/2012 

10/10/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/21/2012 

01/15/2013 
 

 
06/21/2012 

01/15/2013 
100  06/21/2012 

02/20/2013 


-1 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2013 

10/31/2013 
 

 
05/01/2013 

10/31/2013 
100  08/26/2013 

02/04/2014 
-4 

-3 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

12/31/2013 
 

 
11/01/2013 

12/31/2013 
100  02/05/2014 

06/15/2014 
-3 

-6 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Peak Period Time Savings (minutes)

Bond Funding Cost
Adopted:
$283,000
Current Approved:
$283,000
Actual Expenditures:
$283,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle