2013 ROAD REHAB

Description: Rehab various local roads

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City Woodside
Zip Code 94062
 
Senate District
08
Assembly District 21
Congressional District 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Town of Woodside Eunejune Kim 650-851-6790   ekim@woodsidetown.org
Design (PS&E) Phase
Town of Woodside Eunejune Kim 650-851-6790   ekim@woodsidetown.org
Right of Way Phase
Town of Woodside Eunejune Kim 650-851-6790   ekim@woodsidetown.org
Construction Phase
Town of Woodside Dong Nguyen 650-851-6790   dnguyen@woodsidetown.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$267 $0 $267
Non-bond Funding
Local**
$267 $0 $267
 
Total**** $534 $0 $534

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$534 $0 $534 $581 $581 $-47
 
Total* $534 $0 $534 $581 $581 $-47

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/15/2012 

02/11/2013 
 

 
12/15/2012 

02/11/2013 
100  12/15/2012 

02/27/2013 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/15/2012 

03/01/2013 
 

 
12/15/2012 

03/01/2013 
100  12/15/2012 

05/31/2013 


-3 
Begin Right of Way Phase

End Right of Way Phase
12/01/2012 

02/11/2013 
 

 
12/01/2012 

02/11/2013 
100  02/20/2013 

03/20/2013 
-3 

-1 
Begin Construction Phase

End Construction Phase
08/31/2013 

12/31/2013 
 

 
08/31/2013 

12/31/2013 
100  07/30/2013 

03/25/2014 


-3 
Begin Closeout Phase

End Closeout Phase
01/05/2014 

02/28/2014 
 

 
01/05/2014 

02/28/2014 
100  03/26/2014 

07/15/2014 
-3 

-5 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$267,000
Current Approved:
$267,000
Actual Expenditures:
$267,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle