Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
NATIONAL PARK DR IMPROVEMENTS - PHASE 2 |
Description: National Park Dr from SR-62 to Joshua Tree National Park Visitors Center
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Twentynine Palms |
Zip Code | |
Senate District |
18 |
Assembly District | 65 |
Congressional District | 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Twentynine Palms | Richard Pedersen | 7608017615 | richardpedersen@caaprofessionals.com | |
Design (PS&E) Phase |
City of Twentynine Palms | Richard Pedersen | 7608017615 | richardpedersen@caaprofessionals.com | |
Right of Way Phase |
City of Twentynine Palms | Richard Pedersen | 7608017615 | richardpedersen@caaprofessionals.com | |
Construction Phase |
City of Twentynine Palms | Richard Pedersen | 7608017615 | richardpedersen@caaprofessionals.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$400 | $0 | $400 | ||||
Non-bond Funding | |||||||
Local** |
$450 | $0 | $450 | ||||
Total**** | $850 | $0 | $850 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$35 | $0 | $35 | $35 | $35 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$815 | $0 | $815 | $1,045 | $1,045 | $-230 | |
Total* | $850 | $0 | $850 | $1,080 | $1,080 | $-230 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2012 12/31/2012 |
|
09/01/2012 12/31/2012 |
100 | 09/01/2012 03/15/2013 |
0 -2 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/31/2013 09/30/2013 |
|
07/31/2013 09/30/2013 |
100 | 05/28/2013 07/22/2014 |
2 -10 |
Begin Closeout Phase
End Closeout Phase |
10/01/2013 11/01/2013 |
|
10/01/2013 11/01/2013 |
100 | 07/23/2014 01/06/2015 |
-10 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$400,000 |
Current Approved: |
$400,000 |
Actual Expenditures: |
$400,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle