Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
RT 62 - LA HONDA & DUMOSA |
Description: Traffic and Pedestrian Safety Improvements and utility work
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Yucca Valley |
Zip Code | |
Senate District |
31 |
Assembly District | 65 |
Congressional District | 08, 41 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Town of Yucca Valley | Alex Qishta | 7603691265 | aqishta@yucca-valley.org | |
Design (PS&E) Phase |
Town of Yucca Valley | Alex Qishta | 7603691265 | aqishta@yucca-valley.org | |
Right of Way Phase |
Town of Yucca Valley | Alex Qishta | 7603691265 | aqishta@yucca-valley.org | |
Construction Phase |
Town of Yucca Valley | Alex Qishta | 7603691265 | aqishta@yucca-valley.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
LSR |
$138 | $0 | $138 | ||||
SLPP |
$778 | $0 | $778 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,890 | $0 | $1,890 | ||||
Local** |
$896 | $0 | $896 | ||||
Total**** | $3,702 | $0 | $3,702 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$570 | $0 | $570 | $570 | $570 | $0 | |
Design(PS&E) |
$538 | $0 | $538 | $538 | $538 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,594 | $0 | $2,594 | $1,969 | $1,969 | $625 | |
Total* | $3,702 | $0 | $3,702 | $3,077 | $3,077 | $625 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
08/31/2012 01/01/2013 |
|
08/31/2012 01/01/2013 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/31/2013 11/30/2013 |
|
07/31/2013 11/30/2013 |
100 | 07/23/2013 05/20/2014 |
0 -6 |
Begin Closeout Phase
End Closeout Phase |
12/01/2013 03/01/2014 |
|
12/01/2013 03/01/2014 |
100 | 05/21/2014 09/13/2016 |
-6 -31 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$916,000 |
Current Approved: |
$778,000 |
Actual Expenditures: |
$534,252 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle