HERNDON, CLOVIS-FOWLER |
Description: Widen and Improvements on Herndon Ave from Clovis to Fowler Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno |
City | Clovis |
Zip Code | 93612 |
Senate District |
14 |
Assembly District | 29 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Clovis | Ryan Burnett | 559-324-2336 | ryanb@cityofclovis.com | |
Design (PS&E) Phase |
City of Clovis | Sean Smith | 559-324-2363 | seans@cityofclovis.com | |
Right of Way Phase |
City of Clovis | Ryan Burnett | 559-324-2336 | ryanb@cityofclovis.com | |
Construction Phase |
City of Clovis | Steve White | 559-324-2355 | stevenw@cityofclovis.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$799 | $0 | $799 | ||||
Non-bond Funding | |||||||
Local** |
$799 | $0 | $799 | ||||
Total**** | $1,598 | $0 | $1,598 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,598 | $0 | $1,598 | $1,459 | $1,459 | $139 | |
Total* | $1,598 | $0 | $1,598 | $1,459 | $1,459 | $139 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2013 10/01/2013 |
|
06/01/2013 10/01/2013 |
100 | 04/15/2013 08/04/2014 |
2 -10 |
Begin Closeout Phase
End Closeout Phase |
11/01/2013 06/01/2014 |
|
11/01/2013 06/01/2014 |
100 | 08/05/2014 10/10/2014 |
-9 -4 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | ||
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$799,000 |
Current Approved: |
$799,000 |
Actual Expenditures: |
$723,979 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle