HERNDON, CLOVIS-FOWLER

Description: Widen and Improvements on Herndon Ave from Clovis to Fowler Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Clovis
Zip Code 93612
 
Senate District
14
Assembly District 29
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Clovis Ryan Burnett 559-324-2336   ryanb@cityofclovis.com
Design (PS&E) Phase
City of Clovis Sean Smith 559-324-2363   seans@cityofclovis.com
Right of Way Phase
City of Clovis Ryan Burnett 559-324-2336   ryanb@cityofclovis.com
Construction Phase
City of Clovis Steve White 559-324-2355   stevenw@cityofclovis.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$799 $0 $799
Non-bond Funding
Local**
$799 $0 $799
 
Total**** $1,598 $0 $1,598

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,598 $0 $1,598 $1,459 $1,459 $139
 
Total* $1,598 $0 $1,598 $1,459 $1,459 $139

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2013 

10/01/2013 
 

 
06/01/2013 

10/01/2013 
100  04/15/2013 

08/04/2014 


-10 
Begin Closeout Phase

End Closeout Phase
11/01/2013 

06/01/2014 
 

 
11/01/2013 

06/01/2014 
100  08/05/2014 

10/10/2014 
-9 

-4 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$799,000
Current Approved:
$799,000
Actual Expenditures:
$723,979

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle