WILLOW AVE WIDENING - BARSTOW TO ESCALON

Description: Widen Willow Ave between Barstow Ave and Escalon Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14
Assembly District 29
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Lane Miles Added (Mixed)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Design (PS&E) Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Right of Way Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Construction Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$965 $0 $965
Non-bond Funding
Local**
$1,402 $0 $1,402
 
Total**** $2,367 $0 $2,367

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$325 $0 $325 $301 $301 $24
Right of Way
$112 $0 $112 $105 $105 $7
Construction
$1,930 $0 $1,930 $1,962 $1,962 $-32
 
Total* $2,367 $0 $2,367 $2,368 $2,368 $-1

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2010 

05/02/2011 
 

 
02/01/2010 

05/02/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

02/01/2013 
 

 
01/01/2010 

02/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2010 

12/20/2010 
 

 
02/01/2010 

12/20/2010 
100   

 


Begin Construction Phase

End Construction Phase
04/01/2013 

09/01/2013 
 

 
04/01/2013 

09/01/2013 
100  09/26/2013 

02/26/2016 
-6 

-30 
Begin Closeout Phase

End Closeout Phase
09/01/2013 

12/01/2013 
 

 
09/01/2013 

12/01/2013 
100  02/27/2016 

08/23/2016 
-30 

-33 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Lane Miles Added (Mixed)

Bond Funding Cost
Adopted:
$965,000
Current Approved:
$954,917
Actual Expenditures:
$954,917

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle