FRIANT ROAD WIDENING AT SHEPHERD AVE

Description: At the intersection of Friant Rd and Shepherd Ave Widen Friant Rd

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14
Assembly District 23
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
city of fresno steven son 559-621-8674   steven.son@fresno.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$145 $0 $145
Non-bond Funding
Local**
$160 $0 $160
 
Total**** $305 $0 $305

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $0 $15 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$290 $0 $290 $0 $290 $0
 
Total* $305 $0 $305 $0 $305 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

07/01/2008 
 

 
01/01/2005 

07/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2011 

05/31/2013 
 

 
01/01/2011 

05/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
10/01/2013 

05/01/2014 
 

 
10/01/2013 

05/01/2014 
04/03/2014 

12/28/2014 
-6 

-8 
Begin Closeout Phase

End Closeout Phase
06/01/2014 

08/30/2014 
 

 
06/01/2014 

08/30/2014 
10/06/2014 

11/01/2014 
-4 

-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle