TRAFFIC SIGNAL AT SHIELDS &TEMPERANCE

Description: Install a traffic signal with left turn at Shields and Temperance Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14
Assembly District 23
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Design (PS&E) Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Right of Way Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Construction Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$215 $0 $215
Non-bond Funding
Local**
$230 $0 $230
 
Total**** $445 $0 $445

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $14 $14 $1
Right of Way
$0 $0 $0 $5 $5 $-5
Construction
$430 $0 $430 $320 $320 $110
 
Total* $445 $0 $445 $340 $340 $105

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2005 

12/07/2005 
 

 
09/01/2005 

12/07/2005 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2006 

04/30/2013 
 

 
01/01/2006 

04/30/2013 
100  10/07/2013 

01/27/2014 
-95 

-9 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
08/31/2013 

03/31/2014 
 

 
08/31/2013 

03/31/2014 
100  06/05/2014 

03/17/2015 
-9 

-12 
Begin Closeout Phase

End Closeout Phase
04/01/2014 

06/30/2014 
 

 
04/01/2014 

06/30/2014 
100  03/18/2015 

09/09/2015 
-12 

-15 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in Throughput

Bond Funding Cost
Adopted:
$215,000
Current Approved:
$215,000
Actual Expenditures:
$158,932

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle