Caltrans Logo

SIGNAL SYSTEM REHAB

Description: Replace signal equipment along the Caltrain right of way

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
City
Zip Code
 
Senate District
08, 11, 13
Assembly District 12, 19, 21, 22, 23, 24, 27
Congressional District 08, 12, 14, 15, 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Peninsula Corridor Joint Powers Board Rebecca Arthur 6505086368   arthurr@samtrans.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$233 $0 $233
Non-bond Funding
State/Federal*
$2,080 $0 $2,080
Local**
$287 $0 $287
 
Total**** $2,600 $0 $2,600

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,600 $0 $2,600 $7,462 $7,462 $-4,862
 
Total* $2,600 $0 $2,600 $7,462 $7,462 $-4,862

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/08/2012 

08/15/2012 
 

 
05/08/2012 

08/15/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/04/2013 

12/31/2013 
 

 
04/04/2013 

12/31/2013 
100  03/07/2013 

06/30/2019 


-67 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

06/01/2014 
 

 
01/01/2014 

06/01/2014 
100  07/01/2019 

12/31/2019 
-67 

-68 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability

Bond Funding Cost
Adopted:
$233,000
Current Approved:
$233,000
Actual Expenditures:
$187,888

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle