Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SIGNAL SYSTEM REHAB |
Description: Replace signal equipment along the Caltrain right of way
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
|
City | |
Zip Code | |
Senate District |
08, 11, 13 |
Assembly District | 12, 19, 21, 22, 23, 24, 27 |
Congressional District | 08, 12, 14, 15, 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Peninsula Corridor Joint Powers Board | Rebecca Arthur | 6505086368 | arthurr@samtrans.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$233 | $0 | $233 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,080 | $0 | $2,080 | ||||
Local** |
$287 | $0 | $287 | ||||
Total**** | $2,600 | $0 | $2,600 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,600 | $0 | $2,600 | $7,462 | $7,462 | $-4,862 | |
Total* | $2,600 | $0 | $2,600 | $7,462 | $7,462 | $-4,862 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/08/2012 08/15/2012 |
|
05/08/2012 08/15/2012 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/04/2013 12/31/2013 |
|
04/04/2013 12/31/2013 |
100 | 03/07/2013 06/30/2019 |
1 -67 |
Begin Closeout Phase
End Closeout Phase |
01/01/2014 06/01/2014 |
|
01/01/2014 06/01/2014 |
100 | 07/01/2019 12/31/2019 |
-67 -68 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability |
Bond Funding Cost | |
---|---|
Adopted: |
$233,000 |
Current Approved: |
$233,000 |
Actual Expenditures: |
$187,888 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle