Caltrans Logo

TRAFFIC SIGNAL INSTALL @ AUDUBON & COLE

Description: Install traffic signal at Audubon and Cole

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14
Assembly District 23
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)        
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Design (PS&E) Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Right of Way Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Construction Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$181 $0 $181
Non-bond Funding
Local**
$196 $0 $196
 
Total**** $377 $0 $377

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$15 $0 $15 $9 $9 $6
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$362 $0 $362 $319 $319 $43
 
Total* $377 $0 $377 $327 $327 $50

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

12/16/2008 
 

 
01/01/2005 

12/16/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2009 

02/28/2013 
 

 
01/01/2009 

02/28/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
07/31/2013 

03/31/2014 
 

 
07/31/2013 

03/31/2014 
100  04/03/2015 

07/08/2015 
-20 

-15 
Begin Closeout Phase

End Closeout Phase
04/01/2014 

06/30/2014 
 

 
04/01/2014 

06/30/2014 
100  07/09/2015 

12/31/2015 
-15 

-18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours)
Increase in Throughput

Bond Funding Cost
Adopted:
$181,000
Current Approved:
$181,000
Actual Expenditures:
$152,063

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle