2013 LAUREL AVE REHAB |
Description: Repave Laurel Ave
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Lompoc |
Zip Code | 93436 |
Senate District |
19 |
Assembly District | 35 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Lompoc | Alex Ubaldo | 8058758240 | a_ubaldo@ci.lompoc.ca.us | |
Design (PS&E) Phase |
City of Lompoc | Alex Ubaldo | 8058758240 | a_ubaldo@ci.lompoc.ca.us | |
Right of Way Phase |
|||||
Construction Phase |
City of Lompoc | Alex Ubaldo | 8058758240 | a_ubaldo@ci.lompoc.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$77 | $0 | $77 | ||||
Non-bond Funding | |||||||
Local** |
$223 | $0 | $223 | ||||
Total**** | $300 | $0 | $300 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$300 | $0 | $300 | $283 | $283 | $17 | |
Total* | $300 | $0 | $300 | $283 | $283 | $17 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/01/2013 10/01/2013 |
|
08/01/2013 10/01/2013 |
100 | 11/05/2013 06/02/2014 |
-3 -8 |
Begin Closeout Phase
End Closeout Phase |
10/02/2013 12/02/2013 |
|
10/02/2013 12/02/2013 |
100 | 06/03/2014 08/15/2014 |
-8 -9 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
$77,000 |
Current Approved: |
$77,000 |
Actual Expenditures: |
$77,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle