HERNDON EB WIDENING

Description: Widen Herndon Between Brawley and Blythe Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code
 
Senate District
14
Assembly District 23
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Design (PS&E) Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Right of Way Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
Construction Phase
City of Fresno Randy Bell 559-621-8679   randy.bell@fresno.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$818 $0 $818
Non-bond Funding
Local**
$1,226 $0 $1,226
 
Total**** $2,044 $0 $2,044

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$264 $0 $264 $126 $126 $138
Right of Way
$65 $0 $65 $27 $27 $38
Construction
$1,715 $0 $1,715 $1,250 $1,250 $465
 
Total* $2,044 $0 $2,044 $1,403 $1,403 $641

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/10/2012 

02/26/2013 
 

 
10/10/2012 

02/26/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/10/2012 

07/01/2013 
 

 
10/10/2012 

07/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/28/2013 

03/15/2013 
 

 
02/28/2013 

03/15/2013 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2013 

05/30/2014 
 

 
11/01/2013 

05/30/2014 
100  10/24/2013 

08/07/2014 


-2 
Begin Closeout Phase

End Closeout Phase
05/30/2014 

06/30/2014 
 

 
05/30/2014 

06/30/2014 
100  08/08/2014 

03/03/2015 
-2 

-8 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed)
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$818,000
Current Approved:
$818,000
Actual Expenditures:
$625,126

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle