HOSKING AVE WIDENING

Description: Widen Hosking Ave

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93313
 
Senate District
16, 18
Assembly District 30, 32
Congressional District 20, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase in Throughput        
Lane Miles Added (Mixed)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
CITY OF BAKERSFIELD Louis Sun 661-326-3507   lsun@bakersfieldcity.us
Design (PS&E) Phase
CITY OF BAKERSFIELD Louis Sun 661-326-3507   lsun@bakersfieldcity.us
Right of Way Phase
CITY OF BAKERSFIELD Louis Sun 661-326-3507   lsun@bakersfieldcity.us
Construction Phase
CITY OF BAKERSFIELD ROB VOYLES 661-326-3527   rvoyles@bakersfieldcity.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$436 $0 $436
Non-bond Funding
Local**
$436 $0 $436
 
Total**** $872 $0 $872

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$872 $0 $872 $815 $815 $57
 
Total* $872 $0 $872 $815 $815 $57

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  10/17/2012 

02/15/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100  01/10/2013 

10/11/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  04/13/2012 

11/30/2012 


Begin Construction Phase

End Construction Phase
05/01/2013 

08/13/2013 
 

 
05/01/2013 

08/13/2013 
100  11/20/2013 

05/23/2014 
-7 

-9 
Begin Closeout Phase

End Closeout Phase
09/01/2013 

09/30/2013 
 

 
09/01/2013 

09/30/2013 
100  05/24/2014 

02/26/2015 
-9 

-17 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput
Lane Miles Added (Mixed)

Bond Funding Cost
Adopted:
$436,000
Current Approved:
$436,000
Actual Expenditures:
$407,593

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle