PATTERSON AVE SIDEWALK INFILL

Description: Between Debbie Street and Hollister Ave - New gutter, sidewalk, and curb

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Goleta
Zip Code 93117
 
Senate District
19
Assembly District 35
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Goleta Teresa Lopes 805-961-7563   tlopes@cityofgoleta.org
Design (PS&E) Phase
City of Goleta Teresa Lopes 805-961-7563   tlopes@cityofgoleta.org
Right of Way Phase
City of Goleta Teresa Lopes 805-961-7563   tlopes@cityofgoleta.org
Construction Phase
City of Goleta Teresa Lopes 805-961-7563   tlopes@cityofgoleta.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$54 $0 $54
Non-bond Funding
Local**
$281 $0 $281
 
Total**** $335 $0 $335

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $0 $1 $0 $0 $1
Design(PS&E)
$20 $0 $20 $3 $3 $17
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$314 $0 $314 $149 $149 $165
 
Total* $335 $0 $335 $153 $153 $182

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/20/2012 

05/30/2013 
 

 
09/20/2012 

05/30/2013 
100   

08/15/2013 


-3 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/30/2013 

09/30/2013 
 

 
07/30/2013 

09/30/2013 
100  11/19/2013 

07/15/2014 
-4 

-10 
Begin Closeout Phase

End Closeout Phase
09/30/2013 

11/30/2013 
 

 
09/30/2013 

11/30/2013 
100  07/16/2014 

11/13/2014 
-10 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$54,000
Current Approved:
$54,000
Actual Expenditures:
$54,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle