PORT AND WINDY HOLLOW ROAD REHAB |
Description: Rehab Port Road and Windy Hollow
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Mendocino |
City | Point Arena |
Zip Code | 95468 |
Senate District |
02 |
Assembly District | 01 |
Congressional District | 01 |
Caltrans District |
01 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Mendocino Council of Governments | James Sookne | 707-463-1806 | sooknej@dow-associates.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$11 | $0 | $11 | ||||
Non-bond Funding | |||||||
Local** |
$11 | $0 | $11 | ||||
Total**** | $22 | $0 | $22 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$22 | $0 | $22 | $0 | $22 | $0 | |
Total* | $22 | $0 | $22 | $0 | $22 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2013 11/20/2013 |
|
07/01/2013 11/20/2013 |
0 | 03/03/2014 03/28/2014 |
-8 -4 |
Begin Closeout Phase
End Closeout Phase |
03/01/2014 05/31/2014 |
|
03/01/2014 05/31/2014 |
0 | 05/05/2014 05/31/2014 |
-2 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.