Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
ELK GROVE-FLORIN RD/E STOCKTON BLVD |
Description: Realign Elk Grove-florin Road/East Stockton Blvd Intersection
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Elk Grove |
Zip Code | 95624 |
Senate District |
01 |
Assembly District | 15 |
Congressional District | 03 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability | ||
Increase in Throughput |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
City of Elk Grove | Michael Karoly | 916-478-3617 | mkaroly@elkgrovecity.org | |
Right of Way Phase |
|||||
Construction Phase |
City of Elk Grove | Michael Karoly | 916-478-3617 | mkaroly@elkgrovecity.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SLPP |
$419 | $0 | $419 | ||||
Non-bond Funding | |||||||
Local** |
$689 | $0 | $689 | ||||
Total**** | $1,108 | $0 | $1,108 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$8 | $0 | $8 | $1 | $1 | $7 | |
Design(PS&E) |
$212 | $0 | $212 | $257 | $257 | $-45 | |
Right of Way |
$50 | $0 | $50 | $31 | $31 | $19 | |
Construction |
$838 | $0 | $838 | $938 | $938 | $-100 | |
Total* | $1,108 | $0 | $1,108 | $1,228 | $1,228 | $-120 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
11/28/2011 12/12/2011 |
|
11/28/2011 12/12/2011 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2009 01/01/2013 |
|
06/01/2009 01/01/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
11/01/2009 11/01/2012 |
|
11/01/2009 11/01/2012 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2013 12/01/2013 |
|
03/01/2013 12/01/2013 |
100 | 10/28/2013 03/11/2015 |
-8 -15 |
Begin Closeout Phase
End Closeout Phase |
02/01/2014 05/01/2014 |
|
02/01/2014 05/01/2014 |
100 | 03/12/2015 06/15/2015 |
-13 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in System Reliability | ||
Increase in Throughput |
Bond Funding Cost | |
---|---|
Adopted: |
$419,000 |
Current Approved: |
$419,000 |
Actual Expenditures: |
$419,000 |
Status as of December 31, 2023.
SLPP project field information is currently being updated and will be completed by the following reporting cycle