Caltrans Logo

ELK GROVE-FLORIN RD/E STOCKTON BLVD

Description: Realign Elk Grove-florin Road/East Stockton Blvd Intersection

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elk Grove
Zip Code 95624
 
Senate District
01
Assembly District 15
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase in System Reliability        
Increase in Throughput        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
City of Elk Grove Michael Karoly 916-478-3617   mkaroly@elkgrovecity.org
Right of Way Phase
 
Construction Phase
City of Elk Grove Michael Karoly 916-478-3617   mkaroly@elkgrovecity.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$419 $0 $419
Non-bond Funding
Local**
$689 $0 $689
 
Total**** $1,108 $0 $1,108

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$8 $0 $8 $1 $1 $7
Design(PS&E)
$212 $0 $212 $257 $257 $-45
Right of Way
$50 $0 $50 $31 $31 $19
Construction
$838 $0 $838 $938 $938 $-100
 
Total* $1,108 $0 $1,108 $1,228 $1,228 $-120

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/28/2011 

12/12/2011 
 

 
11/28/2011 

12/12/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2009 

01/01/2013 
 

 
06/01/2009 

01/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2009 

11/01/2012 
 

 
11/01/2009 

11/01/2012 
100   

 


Begin Construction Phase

End Construction Phase
03/01/2013 

12/01/2013 
 

 
03/01/2013 

12/01/2013 
100  10/28/2013 

03/11/2015 
-8 

-15 
Begin Closeout Phase

End Closeout Phase
02/01/2014 

05/01/2014 
 

 
02/01/2014 

05/01/2014 
100  03/12/2015 

06/15/2015 
-13 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in System Reliability
Increase in Throughput

Bond Funding Cost
Adopted:
$419,000
Current Approved:
$419,000
Actual Expenditures:
$419,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle