BASE LINE/GREENSPOT ROAD

Description: Traffic Safety and Bikeway Improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Highland
Zip Code
 
Senate District
23, 31
Assembly District 40, 63
Congressional District 08, 51
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)        
Separated Bike/Pedestrian Paths        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City Of Highland Carlos Zamano 909-864-8732, X254   czamano@cityofhighland.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$393 $0 $393
Non-bond Funding
Local**
$581 $0 $581
 
Total**** $974 $0 $974

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $7 $7 $-7
Design(PS&E)
$0 $0 $0 $40 $40 $-40
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$974 $0 $974 $1,022 $1,022 $-48
 
Total* $974 $0 $974 $1,069 $1,069 $-95

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  03/04/2013 

01/29/2016 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/15/2012 

02/15/2013 
 

 
12/15/2012 

02/15/2013 
100  03/04/2013 

10/25/2013 
-3 

-8 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/15/2013 

09/15/2013 
 

 
06/15/2013 

09/15/2013 
100  10/28/2013 

10/13/2015 
-4 

-25 
Begin Closeout Phase

End Closeout Phase
10/15/2013 

12/15/2013 
 

 
10/15/2013 

12/15/2013 
100  10/13/2015 

10/02/2018 
-24 

-58 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles)
Separated Bike/Pedestrian Paths

Bond Funding Cost
Adopted:
$393,000
Current Approved:
$393,000
Actual Expenditures:
$393,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle