NEW MOHAWK GRINDING AND PAVING PROJECT

Description: Grind and remove exisitng pavement and repave with new AC pavement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City Nevada City
Zip Code 95959
 
Senate District
04
Assembly District 01
Congressional District 01
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$41 $0 $41
Non-bond Funding
Local**
$60 $0 $60
 
Total**** $101 $0 $101

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$101 $0 $101 $84 $84 $17
 
Total* $101 $0 $101 $84 $84 $17

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2013 

11/01/2013 
 

 
07/01/2013 

11/01/2013 
100  07/10/2013 

08/13/2013 


Begin Closeout Phase

End Closeout Phase
11/02/2013 

12/01/2013 
 

 
11/02/2013 

12/01/2013 
100  08/14/2013 

10/23/2013 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles

Bond Funding Cost
Adopted:
$41,000
Current Approved:
$41,000
Actual Expenditures:
$41,000

 

Status as of December 31, 2023.