2013 STREET IMPROVEMENT PROGRAM

Description: Rehab the roadway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City El Cerrito
Zip Code 94530
 
Senate District
07
Assembly District 11
Congressional District 07
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles        
Rehabilitated Lane Miles (miles)        
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
El Cerrito Gerardo Avila 510-215-4322   gavila@ci.el-cerrito.ca.us
Design (PS&E) Phase
El Cerrito Gerardo Avila 510-215-4322   gavila@ci.el-cerrito.ca.us
Right of Way Phase
El Cerrito Gerardo Avila 510-215-4322   gavila@ci.el-cerrito.ca.us
Construction Phase
El Cerrito Gerardo Avila 510-215-4322   gavila@ci.el-cerrito.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SLPP
$354 $0 $354
Non-bond Funding
Local**
$478 $0 $478
 
Total**** $832 $0 $832

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$81 $0 $81 $79 $79 $2
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$751 $0 $751 $738 $738 $13
 
Total* $832 $0 $832 $817 $817 $15

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/27/2013 

 
 

 
03/27/2013 

 
100  03/26/2013 

03/27/2013 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2013 

 
 

 
03/01/2013 

 
100  03/04/2013 

06/10/2013 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
09/30/2013 

03/30/2014 
 

 
09/30/2013 

03/30/2014 
100  10/09/2013 

09/30/2014 


-6 
Begin Closeout Phase

End Closeout Phase
04/01/2014 

06/30/2014 
 

 
04/01/2014 

06/30/2014 
25  10/01/2014 

07/14/2015 
-6 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles
Rehabilitated Lane Miles (miles)

Bond Funding Cost
Adopted:
$354,000
Current Approved:
$354,000
Actual Expenditures:
$354,000

 

Status as of December 31, 2023.

SLPP project field information is currently being updated and will be completed by the following reporting cycle