Avenue 52 Grade Separation Project

Description: Construct grade separation bridge on Avenue 52 over Grapefruit Blvd. (Hwy. 111) and the Union Pacific Railroad Mainline.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Coachella
Zip Code 92236
 
Senate District
40
Assembly District 80
Congressional District 45
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Coachella - City Engineer Jonathan Hoy 760-398-5744   jhoy@coachella.org
Design (PS&E) Phase
City of Coachella - City Engineer Jonathan Hoy 760-398-5744   jhoy@coachella.org
Right of Way Phase
City of Coachella - City Engineer Jonathan Hoy 760-398-5744   jhoy@coachella.org
Construction Phase
City of Coachella - Consultant - Athalye Andy Cheah 949-599-5400   acheah@athalyeinc.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$10,000 $-234 $9,766
Non-bond Funding
Local**
$12,200 $11,550 $23,750
Private***
$0 $0 $0
 
Total**** $22,200 $11,316 $33,516

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,578 $90 $2,668 $0 $0 $2,668
Design(PS&E)
$0 $0 $0 $3,135 $3,135 $-3,135
Right of Way
$2,500 $500 $3,000 $5,441 $5,441 $-2,441
Construction
$17,122 $10,726 $27,848 $27,848 $27,848 $0
 
Total* $22,200 $11,316 $33,516 $36,424 $36,424 $-2,908

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2011 

02/01/2012 
09/15/2011 

12/06/2012 
02/01/2011 

07/18/2012 
100  02/01/2011 

07/18/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2011 

12/01/2012 
12/06/2012 

12/06/2012 
07/19/2012 

04/01/2013 
100  07/19/2012 

09/16/2013 


-6 
Begin Right of Way Phase

End Right of Way Phase
02/01/2012 

11/01/2012 
12/06/2012 

06/11/2013 
07/19/2012 

05/31/2013 
100  07/19/2012 

04/01/2013 


Begin Construction Phase

End Construction Phase
07/01/2013 

07/01/2014 
06/11/2013 

12/06/2012 
10/15/2013 

03/31/2015 
100  11/13/2013 

06/30/2016 
-1 

-15 
Begin Closeout Phase

End Closeout Phase
08/01/2014 

02/01/2015 
12/06/2012 

 
04/01/2015 

09/01/2015 
100  07/01/2016 

06/30/2017 
-15 

-22 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$10,000,000
Actual Expenditures:
$9,766,254

 

Status as of December 31, 2023.