Alameda Corridor West Terminus Intermodal Railyard-West Basin Railyard Extension

Description: Construct an intermodal railyard for loading/unloading containers with a direct extension of the West Basin Railyard.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Wilmington
Zip Code
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Nbr of Facilities Modified  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Los Angeles Cristina Sar (310) 732-3627   csar@portla.org
Design (PS&E) Phase
Port of Los Angeles Cristina Sar (310) 732-3627   csar@portla.org
Right of Way Phase
Port of Los Angeles Cristina Sar (310) 732-3627   csar@portla.org
Construction Phase
Port of Los Angeles Cristina Sar (310) 732-3627   csar@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$20,712 $-0 $20,712
Non-bond Funding
Local**
$23,004 $29,271 $52,275
 
Total**** $43,716 $29,271 $72,987

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,292 $1,000 $3,292 $3,113 $3,113 $179
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$41,424 $28,271 $69,695 $69,639 $69,639 $56
 
Total* $43,716 $29,271 $72,987 $72,752 $72,752 $235

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/31/2003 

12/31/2007 
08/22/2012 

08/22/2012 
10/31/2003 

12/31/2007 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/31/2011 

06/30/2013 
08/22/2012 

08/22/2012 
08/31/2011 

06/30/2013 
100   

06/30/2013 


Begin Right of Way Phase

End Right of Way Phase
01/31/2013 

06/30/2013 
08/22/2012 

08/22/2012 
01/31/2013 

06/30/2013 
100   

06/30/2013 


Begin Construction Phase

End Construction Phase
10/31/2013 

04/30/2015 
06/11/2013 

06/11/2013 
11/21/2013 

02/28/2016 
100  11/21/2013 

04/30/2016 


-2 
Begin Closeout Phase

End Closeout Phase
04/30/2015 

04/30/2016 
06/11/2013 

 
02/28/2016 

02/28/2017 
100  04/30/2016 

04/30/2017 
-2 

-2 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr of Facilities Modified 1 1

Bond Funding Cost
Adopted:
$20,712,157
Current Approved:
$20,712,000
Actual Expenditures:
$20,712,000

 

Status as of December 31, 2023.