Alameda Corridor West Terminus Intermodal Railyard-West Basin Railyard Extension |
Description: Construct an intermodal railyard for loading/unloading containers with a direct extension of the West Basin Railyard.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Wilmington |
Zip Code | |
Senate District |
27 |
Assembly District | 54 |
Congressional District | 46 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Port of Los Angeles | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Design (PS&E) Phase |
Port of Los Angeles | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Right of Way Phase |
Port of Los Angeles | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Construction Phase |
Port of Los Angeles | Cristina Sar | (310) 732-3627 | csar@portla.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$20,712 | $-0 | $20,712 | ||||
Non-bond Funding | |||||||
Local** |
$23,004 | $29,271 | $52,275 | ||||
Total**** | $43,716 | $29,271 | $72,987 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,292 | $1,000 | $3,292 | $3,113 | $3,113 | $179 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$41,424 | $28,271 | $69,695 | $69,639 | $69,639 | $56 | |
Total* | $43,716 | $29,271 | $72,987 | $72,752 | $72,752 | $235 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/31/2003 12/31/2007 |
08/22/2012 08/22/2012 |
10/31/2003 12/31/2007 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/31/2011 06/30/2013 |
08/22/2012 08/22/2012 |
08/31/2011 06/30/2013 |
100 | 06/30/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/31/2013 06/30/2013 |
08/22/2012 08/22/2012 |
01/31/2013 06/30/2013 |
100 | 06/30/2013 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/31/2013 04/30/2015 |
06/11/2013 06/11/2013 |
11/21/2013 02/28/2016 |
100 | 11/21/2013 04/30/2016 |
0 -2 |
Begin Closeout Phase
End Closeout Phase |
04/30/2015 04/30/2016 |
06/11/2013 |
02/28/2016 02/28/2017 |
100 | 04/30/2016 04/30/2017 |
-2 -2 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Nbr of Facilities Modified | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$20,712,157 |
Current Approved: |
$20,712,000 |
Actual Expenditures: |
$20,712,000 |
Status as of December 31, 2023.