Baldwin Avenue Grade Separation |
Description: Grade separation project: railroad bridge with double-track capacity and four-lane roadway underpass at Baldwin Avenue in the City of El Monte
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | El Monte |
Zip Code | |
Senate District |
22 |
Assembly District | 49 |
Congressional District | 32 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
ACE Construction Authority | Genichi Kanow | 626-962-9292 | gkanow@theaceproject.org | |
Design (PS&E) Phase |
ACE Construction Authority | Genichi Kanow | 626-962-9292 | gkanow@theaceproject.org | |
Right of Way Phase |
ACE Construction Authority | Genichi Kanow | 626-962-9292 | gkanow@theaceproject.org | |
Construction Phase |
ACE Construction Authority | Genichi Kanow | 626-962-9292 | gkanow@theaceproject.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$37,638 | $-9,899 | $27,739 | ||||
Non-bond Funding | |||||||
Local** |
$43,832 | $0 | $43,832 | ||||
Total**** | $81,470 | $-9,899 | $71,571 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,902 | $0 | $1,902 | $2,171 | $0 | $1,902 | |
Right of Way |
$41,930 | $0 | $41,930 | $36,753 | $0 | $41,930 | |
Construction |
$37,638 | $-9,899 | $27,739 | $27,738 | $0 | $27,739 | |
Total* | $81,470 | $-9,899 | $71,571 | $66,662 | $0 | $71,571 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/28/2000 12/31/2002 |
04/25/2012 04/25/2012 |
02/28/2000 12/31/2002 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/31/2004 12/31/2011 |
04/25/2012 04/25/2012 |
12/31/2004 12/31/2011 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/31/2007 03/31/2012 |
04/25/2012 04/25/2012 |
03/31/2007 03/31/2012 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/31/2012 08/31/2014 |
04/25/2012 04/25/2012 |
08/31/2012 08/31/2014 |
100 | 10/22/2012 04/02/2015 |
-2 -7 |
Begin Closeout Phase
End Closeout Phase |
09/30/2014 01/31/2015 |
04/25/2012 |
09/30/2014 01/31/2015 |
100 | 06/01/2015 09/02/2015 |
-8 -7 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$37,638,000 |
Current Approved: |
$27,739,000 |
Actual Expenditures: |
$27,738,315 |
Status as of December 31, 2023.