Baldwin Avenue Grade Separation

Description: Grade separation project: railroad bridge with double-track capacity and four-lane roadway underpass at Baldwin Avenue in the City of El Monte

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City El Monte
Zip Code
 
Senate District
22
Assembly District 49
Congressional District 32
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
ACE Construction Authority Genichi Kanow 626-962-9292   gkanow@theaceproject.org
Design (PS&E) Phase
ACE Construction Authority Genichi Kanow 626-962-9292   gkanow@theaceproject.org
Right of Way Phase
ACE Construction Authority Genichi Kanow 626-962-9292   gkanow@theaceproject.org
Construction Phase
ACE Construction Authority Genichi Kanow 626-962-9292   gkanow@theaceproject.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$37,638 $-9,899 $27,739
Non-bond Funding
Local**
$43,832 $0 $43,832
 
Total**** $81,470 $-9,899 $71,571

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,902 $0 $1,902 $2,171 $0 $1,902
Right of Way
$41,930 $0 $41,930 $36,753 $0 $41,930
Construction
$37,638 $-9,899 $27,739 $27,738 $0 $27,739
 
Total* $81,470 $-9,899 $71,571 $66,662 $0 $71,571

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/28/2000 

12/31/2002 
04/25/2012 

04/25/2012 
02/28/2000 

12/31/2002 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/31/2004 

12/31/2011 
04/25/2012 

04/25/2012 
12/31/2004 

12/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
03/31/2007 

03/31/2012 
04/25/2012 

04/25/2012 
03/31/2007 

03/31/2012 
100   

 


Begin Construction Phase

End Construction Phase
08/31/2012 

08/31/2014 
04/25/2012 

04/25/2012 
08/31/2012 

08/31/2014 
100  10/22/2012 

04/02/2015 
-2 

-7 
Begin Closeout Phase

End Closeout Phase
09/30/2014 

01/31/2015 
04/25/2012 

 
09/30/2014 

01/31/2015 
100  06/01/2015 

09/02/2015 
-8 

-7 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
$37,638,000
Current Approved:
$27,739,000
Actual Expenditures:
$27,738,315

 

Status as of December 31, 2023.