Hueneme Road Widening

Description: Widen road, between Saviers Road and Arcturus Road, from 2 to 4 lanes with a center turn lane/raised median and left turn pockets. Also widen railroad crossing.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Oxnard
Zip Code 93030
 
Senate District
23
Assembly District 41
Congressional District 23
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  .64    .64  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
City of Oxnard Debbie O'leary 805-200-5283   Debbie.oleary@oxnard.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$1,462 $0 $1,462
Non-bond Funding
Local**
$1,462 $0 $1,462
 
Total**** $2,924 $0 $2,924

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $-0
Construction
$2,924 $0 $2,924 $2,785 $3,610 $-686
 
Total* $2,924 $0 $2,924 $2,785 $2,785 $139

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/10/2008 

03/05/2012 
09/27/2012 

09/27/2012 
03/10/2008 

03/05/2012 
100  03/10/2008 

03/05/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/02/1994 

02/01/2012 
09/27/2012 

09/27/2012 
01/02/1994 

02/01/2012 
100  02/02/1998 

12/28/2012 
-50 

-11 
Begin Right of Way Phase

End Right of Way Phase
01/20/2009 

07/01/2010 
09/27/2012 

09/27/2012 
01/20/2009 

07/01/2010 
100  01/05/2009 

02/02/2010 


Begin Construction Phase

End Construction Phase
02/15/2013 

02/15/2014 
09/27/2012 

09/27/2012 
02/15/2013 

02/15/2014 
100  06/29/2015 

03/31/2016 
-29 

-26 
Begin Closeout Phase

End Closeout Phase
03/01/2014 

09/01/2014 
09/27/2012 

 
03/01/2014 

09/01/2014 
100  04/01/2016 

07/29/2016 
-25 

-23 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) .64 .64

Bond Funding Cost
Adopted:
$1,462,000
Current Approved:
$1,462,000
Actual Expenditures:
$1,436,390

 

Status as of December 31, 2023.