Hueneme Road Widening |
Description: Widen road, between Saviers Road and Arcturus Road, from 2 to 4 lanes with a center turn lane/raised median and left turn pockets. Also widen railroad crossing.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Oxnard |
Zip Code | 93030 |
Senate District |
23 |
Assembly District | 41 |
Congressional District | 23 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | .64 | .64 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
City of Oxnard | Debbie O'leary | 805-200-5283 | Debbie.oleary@oxnard.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$1,462 | $0 | $1,462 | ||||
Non-bond Funding | |||||||
Local** |
$1,462 | $0 | $1,462 | ||||
Total**** | $2,924 | $0 | $2,924 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $-0 | |
Construction |
$2,924 | $0 | $2,924 | $2,785 | $3,610 | $-686 | |
Total* | $2,924 | $0 | $2,924 | $2,785 | $2,785 | $139 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/10/2008 03/05/2012 |
09/27/2012 09/27/2012 |
03/10/2008 03/05/2012 |
100 | 03/10/2008 03/05/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/02/1994 02/01/2012 |
09/27/2012 09/27/2012 |
01/02/1994 02/01/2012 |
100 | 02/02/1998 12/28/2012 |
-50 -11 |
Begin Right of Way Phase
End Right of Way Phase |
01/20/2009 07/01/2010 |
09/27/2012 09/27/2012 |
01/20/2009 07/01/2010 |
100 | 01/05/2009 02/02/2010 |
1 5 |
Begin Construction Phase
End Construction Phase |
02/15/2013 02/15/2014 |
09/27/2012 09/27/2012 |
02/15/2013 02/15/2014 |
100 | 06/29/2015 03/31/2016 |
-29 -26 |
Begin Closeout Phase
End Closeout Phase |
03/01/2014 09/01/2014 |
09/27/2012 |
03/01/2014 09/01/2014 |
100 | 04/01/2016 07/29/2016 |
-25 -23 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | .64 | .64 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,462,000 |
Current Approved: |
$1,462,000 |
Actual Expenditures: |
$1,436,390 |
Status as of December 31, 2023.