US-101 Freeway Performance Initiative |
Description: Widen on-ramps and install ramp metering
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Santa Clara |
City | |
Zip Code | |
Senate District |
15 |
Assembly District | 28 |
Congressional District | 16 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 26.7 | 26.7 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Dina El-Tawansy | 510-286-7236 | Dina_El-Tawansy@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Dina El-Tawansy | 510-286-7236 | Dina_El-Tawansy@dot.ca.gov | |
Right of Way Phase |
Caltrans | Dina El-Tawansy | 510-286-7236 | Dina_El-Tawansy@dot.ca.gov | |
Construction Phase |
Caltrans | Dina El-Tawansy | 510-286-7236 | Dina_El-Tawansy@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$15,000 | $-1,160 | $13,840 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$10,924 | $0 | $10,924 | ||||
Private*** |
$0 | $0 | $0 | ||||
Total**** | $25,924 | $-1,160 | $24,764 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2,120 | $0 | $2,120 | $1,329 | $1,329 | $791 | |
Design(PS&E) |
$2,120 | $0 | $2,120 | $2,778 | $2,778 | $-658 | |
Right of Way |
$67 | $0 | $67 | $9 | $9 | $58 | |
Construction |
$21,617 | $-1,160 | $20,457 | $19,237 | $19,237 | $1,220 | |
Total* | $25,924 | $-1,160 | $24,764 | $23,353 | $23,353 | $1,411 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2010 03/19/2012 |
|
10/01/2010 03/19/2012 |
100 | 10/01/2010 03/19/2012 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/22/2012 05/10/2013 |
|
02/22/2012 05/10/2013 |
100 | 02/22/2012 05/10/2013 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/08/2011 12/04/2012 |
|
10/08/2011 12/04/2012 |
100 | 10/08/2011 12/04/2012 |
0 0 |
Begin Construction Phase
End Construction Phase |
09/03/2013 10/24/2014 |
|
09/03/2013 10/24/2014 |
100 | 11/21/2013 10/30/2015 |
-3 -12 |
Begin Closeout Phase
End Closeout Phase |
10/25/2014 10/24/2015 |
|
10/25/2014 10/24/2015 |
50 | 10/30/2015 10/30/2016 |
-12 -12 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp/Connectors Lane Miles | 26.7 | 26.7 |
Bond Funding Cost | |
---|---|
Adopted: |
$15,000,000 |
Current Approved: |
$13,840,000 |
Actual Expenditures: |
$12,302,656 |
Status as of December 31, 2023.