US-101 Freeway Performance Initiative

Description: Widen on-ramps and install ramp metering

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Clara
City
Zip Code
 
Senate District
15
Assembly District 28
Congressional District 16
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Ramp/Connectors Lane Miles  26.7    26.7  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Dina El-Tawansy 510-286-7236   Dina_El-Tawansy@dot.ca.gov
Design (PS&E) Phase
Caltrans Dina El-Tawansy 510-286-7236   Dina_El-Tawansy@dot.ca.gov
Right of Way Phase
Caltrans Dina El-Tawansy 510-286-7236   Dina_El-Tawansy@dot.ca.gov
Construction Phase
Caltrans Dina El-Tawansy 510-286-7236   Dina_El-Tawansy@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$15,000 $-1,160 $13,840
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$10,924 $0 $10,924
Private***
$0 $0 $0
 
Total**** $25,924 $-1,160 $24,764

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,120 $0 $2,120 $1,329 $1,329 $791
Design(PS&E)
$2,120 $0 $2,120 $2,778 $2,778 $-658
Right of Way
$67 $0 $67 $9 $9 $58
Construction
$21,617 $-1,160 $20,457 $19,237 $19,237 $1,220
 
Total* $25,924 $-1,160 $24,764 $23,353 $23,353 $1,411

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2010 

03/19/2012 
 

 
10/01/2010 

03/19/2012 
100  10/01/2010 

03/19/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/22/2012 

05/10/2013 
 

 
02/22/2012 

05/10/2013 
100  02/22/2012 

05/10/2013 


Begin Right of Way Phase

End Right of Way Phase
10/08/2011 

12/04/2012 
 

 
10/08/2011 

12/04/2012 
100  10/08/2011 

12/04/2012 


Begin Construction Phase

End Construction Phase
09/03/2013 

10/24/2014 
 

 
09/03/2013 

10/24/2014 
100  11/21/2013 

10/30/2015 
-3 

-12 
Begin Closeout Phase

End Closeout Phase
10/25/2014 

10/24/2015 
 

 
10/25/2014 

10/24/2015 
50  10/30/2015 

10/30/2016 
-12 

-12 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Ramp/Connectors Lane Miles 26.7 26.7

Bond Funding Cost
Adopted:
$15,000,000
Current Approved:
$13,840,000
Actual Expenditures:
$12,302,656

 

Status as of December 31, 2023.