Dana Point and San Clemente Crossings

Description: Safety Enhancements on the San Clemente Pier and Senda de la Playa in San Clemente and Palisades/Beach Road Crossing in Dana Point

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Dana Point, San Clemente
Zip Code
 
Senate District
35, 38
Assembly District 73
Congressional District 44, 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0    0  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$2,100 $0 $2,100
Non-bond Funding
Local**
$2,100 $0 $2,100
 
Total**** $4,200 $0 $4,200

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $1,000 $1,000 $1,000 $1,000 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,200 $-1,000 $3,200 $3,649 $3,649 $-449
 
Total* $4,200 $0 $4,200 $4,649 $4,649 $-449

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2011 

03/01/2011 
 

 
02/01/2011 

03/01/2011 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2011 

09/01/2011 
 

 
03/01/2011 

09/01/2011 
100   

09/25/2008 


36 
Begin Right of Way Phase

End Right of Way Phase
06/01/2011 

09/01/2011 
 

 
06/01/2011 

09/01/2011 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2011 

06/01/2012 
 

 
11/01/2011 

06/01/2012 
100   

12/15/2011 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

06/01/2013 
 

 
06/01/2012 

06/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0 0

Bond Funding Cost
Adopted:
$2,100,000
Current Approved:
$2,100,000
Actual Expenditures:
$2,100,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.