San Clemente Beach Trail Crossings

Description: Enhance Safety on seven San Clemente Beach Trail pedestrian crossings

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City San Clemente
Zip Code
 
Senate District
38
Assembly District 73
Congressional District 44
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$2,250 $-80 $2,170
Non-bond Funding
Local**
$2,250 $0 $2,250
 
Total**** $4,500 $-80 $4,420

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$220 $0 $220 $370 $370 $-150
Right of Way
$150 $0 $150 $0 $0 $150
Construction
$4,130 $-80 $4,050 $4,050 $4,050 $0
 
Total* $4,500 $-80 $4,420 $4,420 $4,420 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2011 

06/01/2011 
 

 
01/01/2011 

06/01/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2011 

09/01/2011 
 

 
06/01/2011 

09/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
06/01/2011 

09/01/2011 
 

 
06/01/2011 

09/01/2011 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2011 

06/01/2012 
 

 
09/01/2012 

03/01/2013 
99  05/13/2013 

04/30/2014 
-8 

-14 
Begin Closeout Phase

End Closeout Phase
06/01/2012 

12/01/2012 
 

 
06/01/2012 

12/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
$2,250,000
Current Approved:
$2,250,000
Actual Expenditures:
$2,019,726

 

Status as of December 31, 2023.