Branford Street Grade Crossing Safety Improvement

Description: Crossing Improvement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code
 
Senate District
18
Assembly District 39
Congressional District 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  10    100  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$2,650 $-1,430 $1,220
Non-bond Funding
State/Federal*
$198 $0 $198
Local**
$1,525 $0 $1,525
 
Total**** $4,373 $-1,430 $2,943

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $190 $190 $-190
Design(PS&E)
$200 $0 $200 $208 $208 $-8
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4,173 $-1,430 $2,743 $1,201 $1,201 $1,542
 
Total* $4,373 $-1,430 $2,943 $1,599 $1,599 $1,344

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

12/31/2011 
 

 
01/01/2010 

12/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/31/2013 

04/30/2014 
 

 
04/02/2014 

12/30/2016 
99   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

09/30/2014 
 

 
01/31/2017 

04/30/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 10 100

Bond Funding Cost
Adopted:
$2,650,000
Current Approved:
$1,325,000
Actual Expenditures:
$1,220,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.