Moorpark Avenue Grade Crossing Safety Improvement

Description: Crossing Improvement

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Ventura
City Moorpark
Zip Code
 
Senate District
27
Assembly District 44
Congressional District 26
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  10      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
IIP Augmentation
$0 $0 $0
HRCSA
$4,841 $-29 $4,812
Non-bond Funding
Local**
$200 $0 $200
 
Total**** $5,041 $-29 $5,012

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $943 $943 $-943
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,041 $-29 $5,012 $5,012 $5,012 $0
 
Total* $5,041 $-29 $5,012 $5,955 $5,955 $-943

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/17/2012 

02/28/2013 
 

 
04/17/2012 

02/28/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/31/2013 

12/31/2013 
 

 
07/31/2013 

12/31/2013 
100   

12/31/2017 


-49 
Begin Closeout Phase

End Closeout Phase
02/28/2014 

04/30/2014 
 

 
02/28/2014 

04/30/2014 
 

09/30/2018 


-54 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 10

Bond Funding Cost
Adopted:
$4,841,000
Current Approved:
$4,841,000
Actual Expenditures:
$4,811,795

 

Status as of December 31, 2023.