Navy Drive/BNSF Underpass Part 1 & 2

Description: Improvement Project

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District
05
Assembly District 26
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  10      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,740 $0 $5,740
Non-bond Funding
Local**
$3,173 $0 $3,173
Private***
$184 $0 $184
 
Total**** $9,097 $0 $9,097

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $150 $150 $-150
Design(PS&E)
$730 $0 $730 $539 $539 $191
Right of Way
$370 $0 $370 $0 $0 $370
Construction
$7,997 $0 $7,997 $5,740 $5,740 $2,257
 
Total* $9,097 $0 $9,097 $6,429 $6,429 $2,668

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

07/15/2012 
 

 
 

07/15/2012 
100   

06/25/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2012 

10/30/2013 
 

 
10/01/2012 

10/30/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
12/01/2012 

12/01/2013 
 

 
12/01/2012 

12/01/2013 
100   

 


Begin Construction Phase

End Construction Phase
03/14/2014 

08/01/2015 
 

 
03/14/2014 

08/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/01/2015 
 

08/12/2016 
09/01/2015 

10/01/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 10

Bond Funding Cost
Adopted:
$5,740,000
Current Approved:
$5,740,000
Actual Expenditures:
$5,740,000

 

Status as of December 31, 2023.