San Mateo Bridges GS P2

Description: Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Mateo
Zip Code
 
Senate District
08
Assembly District 09
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Peninsula Corridor Joint Powers Board Rafael Bolon 6505087922   bolonr@samtrans.com
 
Corridor System Management Plan
Carlos Ruiz Carlos Ruiz 916-654-3894   carlos.ruiz@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$9,000 $-136 $8,864
Non-bond Funding
State/Federal*
$20,672 $-1,672 $19,000
Local**
$328 $0 $328
 
Total**** $30,000 $-1,808 $28,192

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2,000 $-1,672 $328 $1,871 $1,871 $-1,543
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$28,000 $-136 $27,864 $8,864 $9,000 $18,864
 
Total* $30,000 $-1,808 $28,192 $10,735 $10,871 $17,321

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

05/27/2009 
 

 
 

05/27/2009 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2012 

11/01/2013 
 

 
09/01/2012 

11/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/08/2014 

05/30/2016 
 

 
05/08/2014 

05/30/2016 
100   

09/30/2016 


-4 
Begin Closeout Phase

End Closeout Phase
06/01/2016 

12/01/2016 
 

 
06/01/2016 

12/01/2016 
100   

12/31/2017 


-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 1

Bond Funding Cost
Adopted:
$9,000,000
Current Approved:
$9,000,000
Actual Expenditures:
$8,854,000

 

Status as of December 31, 2023.