San Mateo Bridges GS P2 |
Description: Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | |
Senate District |
08 |
Assembly District | 09 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Peninsula Corridor Joint Powers Board | Rafael Bolon | 6505087922 | bolonr@samtrans.com | |
Corridor System Management Plan |
Carlos Ruiz | Carlos Ruiz | 916-654-3894 | carlos.ruiz@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$9,000 | $-136 | $8,864 | ||||
Non-bond Funding | |||||||
State/Federal* |
$20,672 | $-1,672 | $19,000 | ||||
Local** |
$328 | $0 | $328 | ||||
Total**** | $30,000 | $-1,808 | $28,192 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$2,000 | $-1,672 | $328 | $1,871 | $1,871 | $-1,543 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$28,000 | $-136 | $27,864 | $8,864 | $9,000 | $18,864 | |
Total* | $30,000 | $-1,808 | $28,192 | $10,735 | $10,871 | $17,321 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/27/2009 |
|
05/27/2009 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2012 11/01/2013 |
|
09/01/2012 11/01/2013 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/08/2014 05/30/2016 |
|
05/08/2014 05/30/2016 |
100 | 09/30/2016 |
0 -4 |
Begin Closeout Phase
End Closeout Phase |
06/01/2016 12/01/2016 |
|
06/01/2016 12/01/2016 |
100 | 12/31/2017 |
0 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$9,000,000 |
Current Approved: |
$9,000,000 |
Actual Expenditures: |
$8,854,000 |
Status as of December 31, 2023.