Warren Avenue Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Fremont
Zip Code
 
Senate District
10
Assembly District 20
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
MPH Increase in Project Area  11.54      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$9,600 $-1,788 $7,812
Non-bond Funding
Local**
$41,851 $10,453 $52,304
Private***
$5,717 $1,161 $6,878
 
Total**** $57,168 $9,826 $66,994

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $7,180 $7,180 $-7,180
Design(PS&E)
$8,709 $-2,857 $5,852 $5,799 $5,799 $53
Right of Way
$9,438 $10,613 $20,051 $19,870 $19,870 $181
Construction
$39,021 $2,070 $41,091 $24,282 $24,282 $16,809
 
Total* $57,168 $9,826 $66,994 $57,131 $57,131 $9,863

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/03/2002 

07/03/2002 
01/20/2011 

01/20/2011 
01/03/2002 

07/03/2002 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/14/2007 

02/25/2011 
03/28/2012 

03/28/2012 
06/14/2007 

02/25/2011 
100   

02/12/2012 


-12 
Begin Right of Way Phase

End Right of Way Phase
05/22/2007 

05/22/2011 
03/28/2012 

03/28/2012 
05/22/2011 

05/22/2011 
100   

02/12/2012 


-9 
Begin Construction Phase

End Construction Phase
11/25/2011 

11/25/2014 
03/28/2012 

03/28/2012 
06/25/2012 

06/25/2015 
96   

 


Begin Closeout Phase

End Closeout Phase
11/25/2014 

04/15/2015 
03/28/2012 

03/28/2012 
06/25/2015 

11/15/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
MPH Increase in Project Area 11.54

Bond Funding Cost
Adopted:
$9,600,000
Current Approved:
$9,600,000
Actual Expenditures:
$7,812,000

 

Status as of December 31, 2023.