Riverside Drive Grade Separation Replacement

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District
22, 24
Assembly District 45
Congressional District 31, 34
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916)654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,000 $0 $5,000
Non-bond Funding
State/Federal*
$44,416 $-97 $44,319
Local**
$2,324 $-116 $2,208
Private***
$6,225 $-27 $6,198
 
Total**** $57,965 $-240 $57,725

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,518 $0 $1,518 $1,517 $1,517 $1
Design(PS&E)
$2,528 $5,120 $7,648 $7,700 $7,700 $-52
Right of Way
$6,000 $-6,000 $0 $0 $0 $0
Construction
$47,919 $640 $48,559 $39,891 $39,940 $8,619
 
Total* $57,965 $-240 $57,725 $49,108 $49,157 $8,568

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

12/01/2005 
 

 
01/01/2005 

12/01/2005 
100   

12/01/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2006 

03/30/2009 
 

 
07/01/2006 

03/30/2009 
100   

06/29/2011 


-27 
Begin Right of Way Phase

End Right of Way Phase
04/30/2009 

01/01/2010 
 

 
04/30/2009 

01/01/2010 
100   

04/01/2010 


-3 
Begin Construction Phase

End Construction Phase
06/30/2010 

12/31/2012 
03/28/2012 

03/28/2012 
06/30/2011 

06/30/2015 
100   

10/01/2017 


-27 
Begin Closeout Phase

End Closeout Phase
01/01/2013 

12/31/2013 
 

 
01/01/2013 

12/31/2013 
 

08/31/2018 


-57 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
$5,000,000
Current Approved:
$5,000,000
Actual Expenditures:
$5,000,000

 

Status as of December 31, 2023.