Riverside Drive Grade Separation Replacement |
Description: Construct a Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | |
Zip Code | |
Senate District |
22, 24 |
Assembly District | 45 |
Congressional District | 31, 34 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | (916)654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$5,000 | $0 | $5,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$44,416 | $-97 | $44,319 | ||||
Local** |
$2,324 | $-116 | $2,208 | ||||
Private*** |
$6,225 | $-27 | $6,198 | ||||
Total**** | $57,965 | $-240 | $57,725 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,518 | $0 | $1,518 | $1,517 | $1,517 | $1 | |
Design(PS&E) |
$2,528 | $5,120 | $7,648 | $7,700 | $7,700 | $-52 | |
Right of Way |
$6,000 | $-6,000 | $0 | $0 | $0 | $0 | |
Construction |
$47,919 | $640 | $48,559 | $39,891 | $39,940 | $8,619 | |
Total* | $57,965 | $-240 | $57,725 | $49,108 | $49,157 | $8,568 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2005 12/01/2005 |
|
01/01/2005 12/01/2005 |
100 | 12/01/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2006 03/30/2009 |
|
07/01/2006 03/30/2009 |
100 | 06/29/2011 |
0 -27 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2009 01/01/2010 |
|
04/30/2009 01/01/2010 |
100 | 04/01/2010 |
0 -3 |
Begin Construction Phase
End Construction Phase |
06/30/2010 12/31/2012 |
03/28/2012 03/28/2012 |
06/30/2011 06/30/2015 |
100 | 10/01/2017 |
0 -27 |
Begin Closeout Phase
End Closeout Phase |
01/01/2013 12/31/2013 |
|
01/01/2013 12/31/2013 |
0 | 08/31/2018 |
0 -57 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,000,000 |
Current Approved: |
$5,000,000 |
Actual Expenditures: |
$5,000,000 |
Status as of December 31, 2023.