North Spring Street Grade Separation Reconstruction

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code
 
Senate District
21, 22, 25
Assembly District 45, 46
Congressional District 31, 34, 35
 
Caltrans District
07
 
 
County/State Route Los Angeles Spr
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
MPH Increase in Project Area  10      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Mary Estensen (916) 654-6664   mary.estensen@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,001 $-8 $4,993
Non-bond Funding
State/Federal*
$32,031 $0 $32,031
Local**
$6,857 $0 $6,857
Private***
$4,877 $0 $4,877
 
Total**** $48,766 $-8 $48,758

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,930 $0 $1,930 $1,930 $1,930 $0
Design(PS&E)
$3,140 $0 $3,140 $3,140 $3,140 $0
Right of Way
$3,862 $0 $3,862 $3,862 $3,862 $0
Construction
$39,834 $-8 $39,826 $26,765 $26,765 $13,061
 
Total* $48,766 $-8 $48,758 $35,697 $35,697 $13,061

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2005 

12/01/2005 
 

09/07/2010 
01/01/2005 

06/30/2011 
100   

06/30/2011 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2006 

03/30/2009 
 

09/07/2010 
07/01/2006 

12/31/2011 
100   

03/31/2012 


-3 
Begin Right of Way Phase

End Right of Way Phase
04/30/2009 

04/30/2010 
09/07/2010 

09/07/2010 
08/01/2008 

06/30/2012 
100   

05/31/2012 


Begin Construction Phase

End Construction Phase
06/30/2010 

12/31/2012 
10/26/2011 

10/26/2011 
12/31/2012 

06/30/2015 
99  02/02/2013 

06/30/2018 
-1 

-37 
Begin Closeout Phase

End Closeout Phase
01/01/2013 

12/31/2013 
10/26/2011 

10/26/2011 
07/01/2015 

06/30/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
MPH Increase in Project Area 10

Bond Funding Cost
Adopted:
$5,001,000
Current Approved:
$5,001,000
Actual Expenditures:
$4,993,000

 

Status as of December 31, 2023.