North Spring Street Grade Separation Reconstruction |
Description: Construct a Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | |
Senate District |
21, 22, 25 |
Assembly District | 45, 46 |
Congressional District | 31, 34, 35 |
Caltrans District |
07 |
County/State Route | Los Angeles Spr |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
MPH Increase in Project Area | 10 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Mary Estensen | (916) 654-6664 | mary.estensen@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$5,001 | $-8 | $4,993 | ||||
Non-bond Funding | |||||||
State/Federal* |
$32,031 | $0 | $32,031 | ||||
Local** |
$6,857 | $0 | $6,857 | ||||
Private*** |
$4,877 | $0 | $4,877 | ||||
Total**** | $48,766 | $-8 | $48,758 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,930 | $0 | $1,930 | $1,930 | $1,930 | $0 | |
Design(PS&E) |
$3,140 | $0 | $3,140 | $3,140 | $3,140 | $0 | |
Right of Way |
$3,862 | $0 | $3,862 | $3,862 | $3,862 | $0 | |
Construction |
$39,834 | $-8 | $39,826 | $26,765 | $26,765 | $13,061 | |
Total* | $48,766 | $-8 | $48,758 | $35,697 | $35,697 | $13,061 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2005 12/01/2005 |
09/07/2010 |
01/01/2005 06/30/2011 |
100 | 06/30/2011 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2006 03/30/2009 |
09/07/2010 |
07/01/2006 12/31/2011 |
100 | 03/31/2012 |
0 -3 |
Begin Right of Way Phase
End Right of Way Phase |
04/30/2009 04/30/2010 |
09/07/2010 09/07/2010 |
08/01/2008 06/30/2012 |
100 | 05/31/2012 |
0 1 |
Begin Construction Phase
End Construction Phase |
06/30/2010 12/31/2012 |
10/26/2011 10/26/2011 |
12/31/2012 06/30/2015 |
99 | 02/02/2013 06/30/2018 |
-1 -37 |
Begin Closeout Phase
End Closeout Phase |
01/01/2013 12/31/2013 |
10/26/2011 10/26/2011 |
07/01/2015 06/30/2016 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
MPH Increase in Project Area | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,001,000 |
Current Approved: |
$5,001,000 |
Actual Expenditures: |
$4,993,000 |
Status as of December 31, 2023.