Broadway-Brazil Street Grade Crossing Improvements

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Glendale, Los Angeles
Zip Code
 
Senate District
21
Assembly District 43
Congressional District 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$4,000 $-3,767 $233
Non-bond Funding
State/Federal*
$2,939 $-265 $2,674
Local**
$2,152 $-321 $1,831
 
Total**** $9,091 $-4,353 $4,738

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$852 $155 $1,007 $975 $975 $32
Right of Way
$0 $268 $268 $0 $0 $268
Construction
$8,239 $-4,776 $3,463 $3,922 $7,689 $-4,226
 
Total* $9,091 $-4,353 $4,738 $4,896 $8,664 $-3,926

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/12/2006 

05/12/2006 
 

 
05/12/2006 

05/12/2006 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

06/01/2009 
 

03/28/2012 
01/01/2008 

04/26/2011 
100   

11/30/2011 


-7 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2009 

03/31/2011 
03/28/2012 

03/28/2012 
07/13/2011 

08/13/2012 
99   

06/01/2014 


-22 
Begin Closeout Phase

End Closeout Phase
03/31/2011 

06/30/2011 
11/04/2010 

11/04/2010 
08/14/2012 

11/15/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
$4,000,000
Current Approved:
$232,677
Actual Expenditures:
$232,492

Click to view the Final Audit Report

 

Status as of December 31, 2023.