Nogales Street Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District
38
Assembly District 24
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  75      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$25,600 $0 $25,600
Non-bond Funding
State/Federal*
$6,098 $29,730 $35,828
Local**
$49,547 $-6,406 $43,141
Private***
$4,185 $8,047 $12,232
 
Total**** $85,430 $31,371 $116,801

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,000 $0 $1,000 $0 $0 $1,000
Design(PS&E)
$2,173 $1,533 $3,706 $4,511 $4,511 $-805
Right of Way
$25,624 $21,150 $46,774 $32,689 $32,689 $14,085
Construction
$56,633 $8,688 $65,321 $35,956 $35,956 $29,365
 
Total* $85,430 $31,371 $116,801 $73,156 $73,156 $43,645

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/30/2003 

01/30/2009 
 

 
07/30/2003 

09/30/2009 
100   

09/30/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/30/2003 

09/30/2009 
 

 
08/30/2003 

12/30/2009 
100   

06/30/2011 


-18 
Begin Right of Way Phase

End Right of Way Phase
01/30/2009 

11/30/2009 
 

 
08/30/2009 

06/02/2010 
100   

08/31/2011 


-15 
Begin Construction Phase

End Construction Phase
02/15/2012 

10/15/2015 
12/05/2012 

12/05/2012 
12/15/2012 

12/15/2015 
100  12/15/2012 

10/31/2017 


-23 
Begin Closeout Phase

End Closeout Phase
01/30/2016 

10/30/2016 
12/05/2012 

12/05/2012 
03/30/2016 

12/30/2016 
100  11/01/2017 

06/30/2018 
-19 

-18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 75

Bond Funding Cost
Adopted:
$25,600,000
Current Approved:
$25,600,000
Actual Expenditures:
$25,600,000

 

Status as of December 31, 2023.