G Street Undercrossing

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City
Zip Code
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2       
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Bambi Jake (916) 654-6945   bjake@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$9,000 $-1,587 $7,413
Non-bond Funding
Local**
$7,200 $0 $7,200
Private***
$1,800 $0 $1,800
 
Total**** $18,000 $-1,587 $16,413

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$1,200 $0 $1,200 $1,614 $1,614 $-414
Right of Way
$2,000 $0 $2,000 $4,382 $4,382 $-2,382
Construction
$14,800 $-1,587 $13,213 $7,413 $7,413 $5,800
 
Total* $18,000 $-1,587 $16,413 $13,409 $13,409 $3,004

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/11/2008 

06/11/2008 
 

 
06/11/2008 

09/04/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/27/2008 

10/31/2009 
 

 
04/27/2008 

10/31/2009 
100   

12/04/2009 


-1 
Begin Right of Way Phase

End Right of Way Phase
01/01/2009 

10/31/2009 
 

 
01/01/2009 

10/31/2009 
100   

05/18/2010 


-7 
Begin Construction Phase

End Construction Phase
03/15/2010 

09/15/2011 
03/28/2012 

03/28/2012 
06/15/2010 

12/15/2011 
100  07/12/2010 

12/30/2011 
-1 

Begin Closeout Phase

End Closeout Phase
08/15/2011 

02/15/2012 
 

 
08/15/2011 

02/15/2012 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

Click to view the Final Audit Report

 

Status as of December 31, 2023.