Kato Road Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Fremont
Zip Code
 
Senate District
10
Assembly District 20
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  12.54      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$10,000 $-876 $9,124
Non-bond Funding
Local**
$42,265 $-2,580 $39,685
 
Total**** $52,265 $-3,456 $48,809

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,176 $0 $1,176 $1,176 $1,176 $0
Design(PS&E)
$7,311 $0 $7,311 $7,311 $7,311 $0
Right of Way
$7,079 $0 $7,079 $7,995 $7,995 $-916
Construction
$36,699 $-3,456 $33,243 $32,986 $32,986 $257
 
Total* $52,265 $-3,456 $48,809 $49,468 $49,468 $-659

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/30/2004 

04/30/2009 
 

 
04/30/2004 

04/30/2009 
100   

04/30/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/30/2009 

12/30/2009 
 

 
04/30/2009 

12/30/2009 
100   

04/30/2011 


-16 
Begin Right of Way Phase

End Right of Way Phase
04/30/2009 

12/30/2009 
 

 
04/30/2009 

12/30/2009 
100   

04/30/2011 


-16 
Begin Construction Phase

End Construction Phase
08/30/2011 

12/30/2012 
03/28/2012 

03/28/2012 
08/30/2011 

12/30/2012 
100   

04/01/2014 


-15 
Begin Closeout Phase

End Closeout Phase
12/30/2012 

12/30/2013 
01/20/2011 

01/20/2011 
12/30/2012 

12/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 12.54

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$10,000,000
Actual Expenditures:
$9,123,986

 

Status as of December 31, 2023.