Sand Canyon Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Orange
City Irvine
Zip Code
 
Senate District
33, 34
Assembly District 70
Congressional District 48
 
Caltrans District
12
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  12      
System Enhancement      65,000  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$8,000 $-1,382 $6,618
Non-bond Funding
State/Federal*
$746 $8,582 $9,328
Local**
$45,858 $-6,214 $39,644
 
Total**** $54,604 $986 $55,590

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $1,060 $1,060 $1,060 $1,060 $0
Design(PS&E)
$2,597 $2,529 $5,126 $4,795 $4,795 $331
Right of Way
$6,492 $1,267 $7,759 $14,138 $14,138 $-6,379
Construction
$45,515 $-3,870 $41,645 $38,149 $44,767 $-3,122
 
Total* $54,604 $986 $55,590 $58,142 $64,760 $-9,170

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2000 

09/30/2003 
 

 
11/01/2000 

09/30/2003 
100   

09/30/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2004 

05/01/2009 
 

 
01/01/2004 

01/29/2010 
100   

09/30/2010 


-8 
Begin Right of Way Phase

End Right of Way Phase
11/01/2008 

11/01/2009 
 

 
11/01/2008 

03/01/2010 
100   

06/30/2010 


-4 
Begin Construction Phase

End Construction Phase
08/01/2010 

01/30/2013 
03/28/2012 

 
04/30/2011 

01/30/2014 
100   

03/31/2014 


-2 
Begin Closeout Phase

End Closeout Phase
02/01/2013 

06/30/2013 
02/01/2016 

12/31/2016 
02/01/2013 

06/30/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 12
System Enhancement 65,000

Bond Funding Cost
Adopted:
$8,000,000
Current Approved:
$6,618,000
Actual Expenditures:
$6,618,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.