6th Street Overcrossing - Bridge |
Description: Construct a Grade Separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | |
Senate District |
06 |
Assembly District | 09 |
Congressional District | 05 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | (916) 654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$17,968 | $-13,131 | $4,837 | ||||
Non-bond Funding | |||||||
Local** |
$17,846 | $-11,859 | $5,987 | ||||
Total**** | $35,814 | $-24,990 | $10,824 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $150 | $150 | $150 | $150 | $0 | |
Design(PS&E) |
$4,355 | $-2,805 | $1,550 | $1,550 | $1,550 | $0 | |
Right of Way |
$3,665 | $-278 | $3,387 | $3,387 | $3,387 | $0 | |
Construction |
$27,794 | $-22,057 | $5,737 | $4,943 | $4,943 | $794 | |
Total* | $35,814 | $-24,990 | $10,824 | $10,030 | $10,030 | $794 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/10/2006 08/20/2007 |
|
03/10/2006 12/11/2007 |
100 | 12/11/2007 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/11/2008 08/31/2009 |
|
03/11/2008 08/31/2009 |
100 | 05/30/2010 |
0 -9 |
Begin Right of Way Phase
End Right of Way Phase |
05/01/2009 08/31/2009 |
|
05/01/2009 08/31/2009 |
100 | 11/30/2009 |
0 -3 |
Begin Construction Phase
End Construction Phase |
02/25/2010 12/31/2011 |
04/07/2010 04/07/2010 |
04/30/2011 10/31/2012 |
100 | 02/28/2010 12/31/2011 |
14 10 |
Begin Closeout Phase
End Closeout Phase |
02/15/2013 02/15/2014 |
01/20/2011 01/20/2011 |
02/15/2013 02/15/2014 |
75 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.