6th Street Overcrossing - Bridge

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code
 
Senate District
06
Assembly District 09
Congressional District 05
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$17,968 $-13,131 $4,837
Non-bond Funding
Local**
$17,846 $-11,859 $5,987
 
Total**** $35,814 $-24,990 $10,824

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $150 $150 $150 $150 $0
Design(PS&E)
$4,355 $-2,805 $1,550 $1,550 $1,550 $0
Right of Way
$3,665 $-278 $3,387 $3,387 $3,387 $0
Construction
$27,794 $-22,057 $5,737 $4,943 $4,943 $794
 
Total* $35,814 $-24,990 $10,824 $10,030 $10,030 $794

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/10/2006 

08/20/2007 
 

 
03/10/2006 

12/11/2007 
100   

12/11/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/11/2008 

08/31/2009 
 

 
03/11/2008 

08/31/2009 
100   

05/30/2010 


-9 
Begin Right of Way Phase

End Right of Way Phase
05/01/2009 

08/31/2009 
 

 
05/01/2009 

08/31/2009 
100   

11/30/2009 


-3 
Begin Construction Phase

End Construction Phase
02/25/2010 

12/31/2011 
04/07/2010 

04/07/2010 
04/30/2011 

10/31/2012 
100  02/28/2010 

12/31/2011 
14 

10 
Begin Closeout Phase

End Closeout Phase
02/15/2013 

02/15/2014 
01/20/2011 

01/20/2011 
02/15/2013 

02/15/2014 
75   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

Click to view the Final Audit Report

 

Status as of December 31, 2023.