Caltrans Logo

Park Boulevard at Harbor Drive Pedestrian Bridge

Description: Grade separation of rail, vehicular, pedestrian traffic at intersection of Park Blvd and Harbor Dr in downtown San Diego

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code
 
Senate District
39
Assembly District 76
Congressional District 53
 
Caltrans District
11
 
 
County/State Route San Diego PS
Postmile Begin/End 268.8 268.8
Project Benefits
 Benefit Baseline Actual
System Enhancement  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
IIP Augmentation
$0 $0 $0
HRCSA
$6,000 $0 $6,000
Non-bond Funding
State/Federal*
$4,800 $0 $4,800
Local**
$15,756 $444 $16,200
 
Total**** $26,556 $444 $27,000

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $550 $550 $-550
Design(PS&E)
$0 $0 $0 $2,216 $2,216 $-2,216
Right of Way
$0 $444 $444 $383 $383 $61
Construction
$26,556 $0 $26,556 $21,952 $21,952 $4,604
 
Total* $26,556 $444 $27,000 $25,101 $25,101 $1,899

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/23/2004 

06/05/2006 
 

 
08/23/2004 

06/05/2006 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/23/2004 

07/17/2007 
 

 
08/23/2004 

07/17/2007 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/08/2005 

07/24/2007 
 

 
02/08/2005 

07/24/2007 
100   

 


Begin Construction Phase

End Construction Phase
06/26/2008 

01/01/2010 
 

 
06/26/2008 

01/01/2010 
90   

 


Begin Closeout Phase

End Closeout Phase
01/02/2010 

06/01/2010 
 

 
01/02/2010 

06/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0

Bond Funding Cost
Adopted:
$6,000,000
Current Approved:
$6,000,000
Actual Expenditures:
$6,000,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.