Jerrold Avenue Bridge Grade Separation

Description: Construct a Grade Separation over Jerrold Avenue in the City of San Francisco.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Francisco
City
Zip Code
 
Senate District
03
Assembly District 13
Congressional District 08
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0    0  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$10,000 $-7,332 $2,668
Non-bond Funding
State/Federal*
$27,260 $-18,813 $8,447
Local**
$4,359 $-3,892 $467
 
Total**** $41,619 $-30,037 $11,582

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$800 $192 $992 $981 $981 $11
Design(PS&E)
$2,000 $-1,105 $895 $884 $884 $11
Right of Way
$0 $0 $0 $176 $176 $-176
Construction
$38,819 $-29,124 $9,695 $9,663 $9,663 $32
 
Total* $41,619 $-30,037 $11,582 $11,704 $11,704 $-122

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2006 

09/30/2009 
 

 
12/01/2006 

09/30/2009 
100   

09/11/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2009 

03/30/2010 
 

12/10/2010 
10/01/2009 

03/30/2010 
100   

06/30/2010 


-3 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

02/26/2010 


Begin Construction Phase

End Construction Phase
07/01/2010 

10/31/2011 
01/19/2011 

01/19/2011 
06/03/2010 

09/03/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2011 

05/01/2012 
 

 
11/01/2011 

05/01/2012 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0 0

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$2,785,509
Actual Expenditures:
$2,785,590

Click to view the Final Audit Report

 

Status as of December 31, 2023.