Port of Stockton Expressway

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City
Zip Code
 
Senate District
05
Assembly District 26
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$4,400 $-2,863 $1,537
Non-bond Funding
State/Federal*
$1,500 $4,901 $6,401
Local**
$5,100 $-4,880 $220
Private***
$500 $-71 $429
 
Total**** $11,500 $-2,913 $8,587

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$500 $50 $550 $550 $550 $0
Design(PS&E)
$1,000 $-450 $550 $550 $550 $0
Right of Way
$0 $235 $235 $235 $235 $0
Construction
$10,000 $-2,748 $7,252 $7,215 $7,215 $37
 
Total* $11,500 $-2,913 $8,587 $8,550 $8,550 $37

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2008 

11/01/2009 
 

 
12/01/2008 

04/15/2010 
100   

04/08/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2009 

03/01/2010 
 

 
04/15/2010 

06/01/2010 
100   

10/15/2010 


-5 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

06/23/2010 


Begin Construction Phase

End Construction Phase
06/01/2010 

09/01/2011 
03/28/2012 

03/28/2012 
04/15/2011 

06/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2011 

12/01/2011 
 

 
09/01/2011 

12/01/2011 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0 1

Bond Funding Cost
Adopted:
$4,400,000
Current Approved:
$1,537,000
Actual Expenditures:
$1,537,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.