Eight Mile Road/UPRR (West) Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District
05
Assembly District 10
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  33.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$8,500 $-1,076 $7,424
Non-bond Funding
Local**
$16,500 $0 $16,500
Private***
$0 $0 $0
 
Total**** $25,000 $-1,076 $23,924

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,100 $0 $1,100 $600 $600 $500
Design(PS&E)
$2,200 $0 $2,200 $2,200 $2,200 $0
Right of Way
$4,300 $0 $4,300 $1,000 $1,000 $3,300
Construction
$17,400 $-1,076 $16,324 $15,314 $15,314 $1,010
 
Total* $25,000 $-1,076 $23,924 $19,114 $19,114 $4,810

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2006 

07/01/2007 
 

 
04/01/2006 

07/01/2007 
100   

07/31/2007 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2007 

01/01/2010 
 

 
12/01/2007 

01/01/2010 
100   

12/01/2009 


Begin Right of Way Phase

End Right of Way Phase
08/01/2008 

12/01/2009 
 

 
08/01/2008 

12/01/2009 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2010 

12/01/2011 
03/28/2012 

03/28/2012 
10/01/2010 

05/07/2014 
99   

 


Begin Closeout Phase

End Closeout Phase
12/01/2011 

03/01/2012 
 

 
12/01/2011 

03/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 33.4

Bond Funding Cost
Adopted:
$8,500,000
Current Approved:
$8,081,000
Actual Expenditures:
$7,423,785

Click to view the Final Audit Report

 

Status as of December 31, 2023.