Lower Sacramento Road at UPRR Grade Separation

Description: Construct a Grade Separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District
05
Assembly District 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  27      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$10,000 $-3,516 $6,484
Non-bond Funding
State/Federal*
$0 $5,100 $5,100
Local**
$24,000 $-4,760 $19,240
Private***
$0 $0 $0
 
Total**** $34,000 $-3,176 $30,824

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$460 $140 $600 $600 $600 $0
Design(PS&E)
$2,000 $200 $2,200 $2,200 $2,200 $0
Right of Way
$1,500 $0 $1,500 $1,750 $1,750 $-250
Construction
$30,040 $-3,516 $26,524 $18,653 $18,653 $7,871
 
Total* $34,000 $-3,176 $30,824 $23,203 $23,203 $7,621

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2006 

07/01/2007 
 

 
04/01/2006 

07/01/2007 
100   

07/31/2007 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2007 

01/01/2010 
 

 
12/01/2007 

01/01/2010 
100   

12/28/2009 


Begin Right of Way Phase

End Right of Way Phase
12/01/2007 

01/01/2010 
 

 
08/01/2008 

12/01/2009 
100   

01/29/2010 


-2 
Begin Construction Phase

End Construction Phase
07/01/2010 

12/01/2011 
03/28/2012 

03/28/2012 
10/01/2010 

11/01/2012 
99  07/01/2010 

 


Begin Closeout Phase

End Closeout Phase
12/01/2011 

03/01/2012 
 

 
12/01/2011 

03/01/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 27

Bond Funding Cost
Adopted:
$10,000,000
Current Approved:
$6,877,000
Actual Expenditures:
$6,483,506

Click to view the Final Audit Report

 

Status as of December 31, 2023.