San Mateo Bridges Grade Separation

Description: Construct Grade Separations

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City
Zip Code
 
Senate District
08
Assembly District 19
Congressional District 12
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
System Enhancement  0    0  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Caltrans Carlos Ruiz (916) 654-3894   carlos.ruiz@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
HRCSA
$5,000 $-4,045 $955
Non-bond Funding
State/Federal*
$36,555 $-27,587 $8,968
Local**
$2,090 $-1,865 $225
Private***
$2,876 $-2,876 $0
 
Total**** $46,521 $-36,373 $10,148

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$440 $0 $440 $440 $440 $0
Design(PS&E)
$4,900 $826 $5,726 $4,161 $4,161 $1,565
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$41,181 $-37,199 $3,982 $3,678 $3,678 $304
 
Total* $46,521 $-36,373 $10,148 $8,279 $8,279 $1,869

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2004 

08/31/2009 
 

 
06/01/2004 

08/31/2009 
100   

05/27/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2006 

09/01/2009 
 

01/19/2011 
01/01/2006 

10/06/2010 
100   

10/06/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

03/01/2010 


Begin Construction Phase

End Construction Phase
12/01/2009 

05/31/2011 
01/19/2011 

03/23/2011 
10/07/2010 

06/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2011 

12/01/2011 
01/19/2011 

01/19/2011 
03/31/2012 

04/01/2012 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
System Enhancement 0 0

Bond Funding Cost
Adopted:
$5,000,000
Current Approved:
$1,107,072
Actual Expenditures:
$955,116

Click to view the Final Audit Report

 

Status as of December 31, 2023.