San Mateo Bridges Grade Separation |
Description: Construct Grade Separations
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | |
Zip Code | |
Senate District |
08 |
Assembly District | 19 |
Congressional District | 12 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Caltrans | Carlos Ruiz | (916) 654-3894 | carlos.ruiz@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
HRCSA |
$5,000 | $-4,045 | $955 | ||||
Non-bond Funding | |||||||
State/Federal* |
$36,555 | $-27,587 | $8,968 | ||||
Local** |
$2,090 | $-1,865 | $225 | ||||
Private*** |
$2,876 | $-2,876 | $0 | ||||
Total**** | $46,521 | $-36,373 | $10,148 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$440 | $0 | $440 | $440 | $440 | $0 | |
Design(PS&E) |
$4,900 | $826 | $5,726 | $4,161 | $4,161 | $1,565 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$41,181 | $-37,199 | $3,982 | $3,678 | $3,678 | $304 | |
Total* | $46,521 | $-36,373 | $10,148 | $8,279 | $8,279 | $1,869 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2004 08/31/2009 |
|
06/01/2004 08/31/2009 |
100 | 05/27/2009 |
0 3 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2006 09/01/2009 |
01/19/2011 |
01/01/2006 10/06/2010 |
100 | 10/06/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | 03/01/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2009 05/31/2011 |
01/19/2011 03/23/2011 |
10/07/2010 06/30/2011 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2011 12/01/2011 |
01/19/2011 01/19/2011 |
03/31/2012 04/01/2012 |
25 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
System Enhancement | 0 | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,000,000 |
Current Approved: |
$1,107,072 |
Actual Expenditures: |
$955,116 |
Status as of December 31, 2023.